Archived

This content is available here strictly for research, reference, and/or recordkeeping and as such it may not be fully accessible. If you work or study at University of Kentucky and would like to request an accessible version, please use the SensusAccess Document Converter.

Location

Lexington, Kentucky

Start Date

7-5-2026 9:30 AM

End Date

7-5-2026 10:00 AM

Description

Stantec recently supported commissioning a flue gas desulfurization (FGD) Wastewater Treatment System in accordance with the 2020 Environmental Protection Agency (EPA) Effluent Limitations Guidelines (ELG) Rule, which requires that coal fired power plants meet their more stringent requirements by December 31, 2025. With the addition of the 2024 EPA ELG Rule, coal fired power plants will now be expected to move to zero liquid discharge (ZLD) systems or permanently cease coal combustion by 2034. Due to this change, it is likely that coal fired power plants will be looking to design and install ZLD systems within the next decade. While the ZLD systems are more complex than the current wastewater treatment systems that now exist, the lessons learned from the current FGD projects will prove to be beneficial as the deadline for the 2024 Rule approaches. The paper will focus on design considerations, operating procedures, and opportunities to improve safety that were relevant to the commissioning process. By studying the circumstances that led to each of these learning moments, engineers and operators of all levels of experience can learn better ways to design and commission a FGD wastewater treatment system.

Document Type

Presentation

Archival?

Archival

Share

COinS
 
May 7th, 9:30 AM May 7th, 10:00 AM

Lessons Learned: Commissioning an FGD Wastewater Treatment System

Lexington, Kentucky

Stantec recently supported commissioning a flue gas desulfurization (FGD) Wastewater Treatment System in accordance with the 2020 Environmental Protection Agency (EPA) Effluent Limitations Guidelines (ELG) Rule, which requires that coal fired power plants meet their more stringent requirements by December 31, 2025. With the addition of the 2024 EPA ELG Rule, coal fired power plants will now be expected to move to zero liquid discharge (ZLD) systems or permanently cease coal combustion by 2034. Due to this change, it is likely that coal fired power plants will be looking to design and install ZLD systems within the next decade. While the ZLD systems are more complex than the current wastewater treatment systems that now exist, the lessons learned from the current FGD projects will prove to be beneficial as the deadline for the 2024 Rule approaches. The paper will focus on design considerations, operating procedures, and opportunities to improve safety that were relevant to the commissioning process. By studying the circumstances that led to each of these learning moments, engineers and operators of all levels of experience can learn better ways to design and commission a FGD wastewater treatment system.