Abstract

Three recently completed road construction projects were investigated to determine Kentucky Transportation Cabinet (KYTC) effectiveness in implementing project commitments (including environmental commitments). Documentation was obtained from KYTC districts in which the projects were constructed and KYTC officials involved with the projects from planning through construction were interviewed. The projects were inspected to audit completion of project commitments. Key stakeholders (officials of local governments, resource agencies, MPOs, interest groups, and adjacent landowners) were interviewed about the projects. They were asked to grade KYTC for implementation of project commitments using a standard report card format. The findings for these investigations are presented. The auditing procedure employed in this study can be used to rate future KYTC projects, identify problems, and suggest solutions.

Report Date

3-2005

Report Number

KTC-04-30/SPR210-00-1F

Digital Object Identifier

http://dx.doi.org/10.13023/KTC.RR.2004.30

Notes

The contents of this report reflect the views of the authors, who are responsible for the facts and accuracy of the data presented herein. The contents do not necessarily reflect the official views or policies of the University of Kentucky nor the Kentucky Transportation Cabinet. This report does not constitute a standard, specification, or regulation.

Share

COinS